The proposal

What was on the table

Deltona Corporation filed a Comprehensive Plan Amendment and a zoning change to convert land along the CR 491 and Tram Road corridor to Heavy Industrial use. The stated use was an industrial park with potential for an AI or hyperscale data center.

Heavy Industrial zoning is rarely reversed. Once approved, a data center or other heavy industrial use could have moved forward with limited or no additional public hearings. No enforceable limits on power, water, or noise had been defined.

Applications
CPA-2025-00012 & CPA/AA-2025-00013
Applicant
Deltona Corporation
Location
Lecanto / Holder, CR 491 & Tram Road
Acres in application
~813
Total footprint sought
1,300+ acres
Requested zoning
Heavy Industrial

The campaign

How residents responded

What began as neighbors comparing notes grew into one of the fastest-growing citizen land-use campaigns in Florida, with more than 6,000 people supporting the effort.

Research

Volunteers published plain-language breakdowns of the applications, the community impacts, and the technical facts, with every source cited.

A public forum

The Unite Citrus Public Forum on May 23, 2026 at the Old Schoolhouse in Hernando brought residents together to learn about the proposal and how to act.

Showing up

Residents filed public comments, contacted commissioners, and filled the hearing room. NDCC took part in the PDC hearing as a public intervenor.

“People here choose Citrus County because of its rural character, springs, waterways, wildlife, and slower pace of life. They don’t want to wake up one day and find themselves living next to an industrial AI corridor.”

Athalene Bulla, Hernando resident near the proposed site

The outcome

Three votes in five days

The Planning & Development Commission recommended denial unanimously. Three days later the County Commission refused to postpone the case, and the applicant withdrew.

  1. 7–0Planning & Development Commission votes to deny
  2. 5–0County Commission denies a continuance
  3. Deltona withdraws its applicationsThe rezoning is off the table.

What comes next

Why we're still watching

A withdrawn application is not a permanent answer. The land is still there, demand for data centers in Florida keeps growing, and the county does not yet have rules written for facilities of this size.

NDCC now monitors land use and zoning decisions countywide and is working toward a Citrus County ordinance that permanently prohibits hyperscale data centers.